CASAN PLAN 05 — CI/CD & Release Gate

Status 2026-07-06: CI gate MVP implemented + locally syntax/filter verified. A reusable local/CI gate script now exists, and a Gitea Actions workflow is wired to run it on main push/PR. Package publishing/release automation is still planned.

Delivered

Capability Where Verification
One-command harness CI gate packages/casan-harness/scripts/bash/ci-harness-gate.sh bash -n; local suites are callable in safe order
Safe test order run-casan4 runs first because it rewrites .specify/logs; hardening suites run after script order
Per-suite timeout CASAN_CI_STEP_TIMEOUT_SEC protects CI from hung model/security subprocesses full gate attempt exposed a long A6 run; timeout wrapper added
Filtered local verification `CASAN_CI_SUITE_FILTER='phase2-sourcegen phase10-traceability'`
Source-gen gate included phase2-sourcegen-tests.sh included sourcegen 10/0
Traceability gate included phase10-traceability-tests.sh included traceability 3/0
Frontend runtime tests included npm test -w frontend when npm is present frontend Vitest path
Optional Docker local-prod lab CASAN_CI_RUN_INFRA_LAB=1 runs phase-prod-infra-lab-tests.sh only when Docker Compose is available skip-aware by default
Gitea Actions workflow .gitea/workflows/harness-ci.yml workflow calls ci-harness-gate.sh

Gate contents

Required gate:

  • run-casan4-harness-tests.sh
  • adversarial-harness-tests.sh
  • phase1-track-a-tests.sh
  • phase2-track-c-tests.sh
  • phase2-sourcegen-tests.sh
  • phase3-evidence-pack-tests.sh
  • phase3-model-router-tests.sh
  • phase-h5-approval-tests.sh
  • phase-h5-infra-tests.sh
  • phase-h6-agentops-tests.sh
  • phase-c7-incident-tests.sh
  • phase-h4-multilingual-tests.sh
  • phase-c6-sandbox-tests.sh
  • phase-h4-split-inject-tests.sh
  • phase10-traceability-tests.sh
  • npm test -w frontend when npm is available

Optional gate:

  • phase-prod-infra-lab-tests.sh when CASAN_CI_RUN_INFRA_LAB=1 and Docker Compose is available.

Remaining work

Priority Work Done when
P1 Run the workflow on the real Gitea runner Gitea run shows green CASAN Harness CI on main
P2 Investigate slow/hung A6 full-gate local run phase1-track-a-tests.sh A6 completes under timeout consistently on Mac/runner
P3 Decide Docker availability on runner CASAN_CI_RUN_INFRA_LAB=1 is enabled only if runner mounts Docker safely
P4 Package/release automation npm pack or release artifact for fpt-casan-sdd-harness is generated and versioned
P5 Backend full npm test unblock Prisma/MySQL-vs-SQLite test-infra mismatch is resolved or split into a proper MySQL service job
P6 Branch protection Merge requires green CI gate

Local commands

cd "$(git rev-parse --show-toplevel)"  # repo root (app promoted here)
bash -n packages/casan-harness/scripts/bash/ci-harness-gate.sh
CASAN_CI_RUN_FRONTEND=1 CASAN_CI_RUN_INFRA_LAB=0 bash packages/casan-harness/scripts/bash/ci-harness-gate.sh
CASAN_CI_RUN_INFRA_LAB=1 bash packages/casan-harness/tests/phase-prod-infra-lab-tests.sh

Notes

  • backend npm test is not part of the required CI gate yet because the current repo has a known pre-existing mismatch: schema.prisma is MySQL-oriented but backend/scripts/setup-sqlite.mjs applies migrations to SQLite.
  • The workflow installs Node 20 inside the Gitea job if the runner image does not already provide node/npm.